Due to the construction of the Yamula Dam in Kayseri, the road leading to Felahiye Village was going to stay under water. While the dam was almost complete and about to collect water, a new bridge was planned on the dam reservoir. For this design and build contract, ESPM worked together with its contractor sister company, and a totally new bridge was planned and built within 6 months. Design duration was 1 months to start construction. Viaduct length was 410 meters, containing 12 precast concrete beams of 36 meters each. Base heights were 50 meters. Design leaded the fast completion of construction.
Services provided include:
- Evaluating cartography
- Geotechnical survey and geotechnical report.
- Determining viaduct characteristics.
- Design and calculation of viaduct.
- Detail design, quantity and cost analysis.